Enerpal completes the execution of a new Off-grid self-consumption power plant of 17.76 kW peak power capacity in Castile and Leon (Spain).
In the fourth quarter of 2016, Enerpal has completed the installation of the Off-grid solar photovoltaic Self-consumption power plant for the electrical supply of an Electromechanical Workshop of agricultural machinery and single-family Housing.
The installation consists of 84 solar photovoltaic modules with total installed peak power capacity of 17.76 kW, 3 inverters of 6 kW of unit rated power, bank of batteries with storage capacity of 122.304 kWh and elements of management and control.